New Nukes in PA
From the Nuclear Information and Resource Service: Here is a copy of a memo we received from the Nuclear Regulatory Commission concerning a public meeting in Bloomsburg, Pennsylvania on August 19, 2008, to discuss the upcoming application for a Construction/Operating License for a new atomic reactor in PA from Pennsylvania Power & Light. We hope as many of you as possible will make it to this meeting and let PPL and the NRC know that Pennsylvania opposes new reactors! nirsnet@nirs.org; www.nirs.org
SUBJECT: PUBLIC OUTREACH MEETING ON THE COMBINED LICENSE
APPLICATION PROCESS FOR THE PROPOSED BELL BEND
NUCLEAR POWER PLANT
DATE & TIME: August 19, 2008
6:00 p.m. to 9:30 p.m.
LOCATION: Bloomsburg University ’s Kehr Union Ballroom Lobby and Ballroom
400 East Second Street
Bloomsburg, PA 17815
PURPOSE: The U. S. Nuclear Regulatory Commission (NRC) staff will discuss the
role that the NRC will play in the anticipated review of PPL’s application
for a combined license including details of the safety and environmental
reviews. A key topic is how and when the public may participate in NRC
processes, if so desired. The public is encouraged to ask questions about
the NRC’s review of the Bell Bend combined license application (COLA).
CATEGORY 3: * This is a Category 3 Meeting. The public is invited to participate in this
meeting by providing comments and asking questions throughout the
meeting.
CONTACTS: Primary
Michael A. Canova, NRO/DNRL Surinder Arora, NRO/DNRL
301-415-0737 301-415-1421
michael.canova@nrc.gov surinder.arora@nrc.gov
* Commission's Policy Statement on AEnhancing Public Participation in NRC Meetings@
(67 FR 36920), May 28, 2002
J. Colaccino -2-
PARTICIPANTS: Participants from the NRC include the following members from the Office
of New Reactors (NRO).
NRC
J. Colaccino, NRO
M. Canova, NRO
S. Arora, NRO
I. Yu, NRO
J. Jennings, NRO
L. Rakovan, EDO
ADAMS ACCESSION NO.: ML082120588 NRC-001
OFFICE PM:DNRL/NARP/NRO LA:DNRL/NARP/NRO BC:DNRL/NARP/NRO
OFFICIAL RECORD COPY
OPEN HOUSE AND PUBLIC OUTREACH MEETING
PPL APPLICATION FOR A COMBINED LICENSE
BELL BEND
August 19, 2008
Time (approximate) Topic Presenter
6:00 p.m. Open House (poster session in lobby) NRC
7:00 p.m. Public Outreach Meeting Begins.
Introductions/Opening Remarks
NRC
7:15 p.m. NC Staff Presentations
• NRC: Who We Are And What We Do
• Overview of COLA Review Process
o Safety Review
o Environmental Review
o How the public may participate
• Construction Inspection
NRC
7:45 p.m. Open forum for public questions and comments
on NRC processes
Unit 2
9:30 p.m.
Adjourn